When does each Section 20 notice have to go out?
Put in the date you want to sign the contract and say what is being consulted on. The tool works backwards to the latest date for each notice and each 30-day window, and shows the cap that applies if a step is missed.Put in the signing date and say what is being consulted on. The tool works backwards to the latest date for each notice and window, and shows the cap if a step is missed.
What you get back
- Which schedule your dates come from
Named on the result, with the regulation that routes you to it. Works under a long-term agreement the block already has run to three dates. Every other route has five, and a director must not read agreement dates as works dates.
SI 2003/1987 regs. 5, 7 (opens in new tab) - The latest date for each notice
Worked back from your signing date, with your own allowance for getting the estimates in. Each stop says whether the date comes from the Regulations or from that allowance.
Sch 1–4 (opens in new tab) - Each 30-day window
When observations can be made, and the earliest the block may go ahead. The period begins with the date of the notice, so the notice’s own day is day one. A notice served after its date here pushes the signing date back. Going ahead before a window has closed is a missed step.
reg. 2 (opens in new tab) (relevant period) - What a missed step costs
The block can recover no more than £250 from each flat, or £100 a flat in each accounting period for an agreement, unless a tribunal dispenses with the consultation requirements.
LTA 1985 s.20(1), (7), s.20ZA (opens in new tab); regs. 4(1), 6 (opens in new tab) - Where the file goes next
Who must be served, what proof of service to keep, and how the observations are logged. If a step is ever questioned, the block has to show what it did, and a tribunal deciding dispensation looks at what leaseholders lost.
SI 2003/1987 Schs 1–4, para 1(1) (opens in new tab); Daejan v Benson [2013] UKSC 14 (opens in new tab)
There are other timeline calculators. This one asks which route you are on before it gives you dates, tells you what it costs the block to get one wrong, and hands the dates to a file that keeps the proof.